How to make activity wait/sleep for specific date

Confluence User - 14 Jul, 2020

Hello

How to make an assignment wait dor a specific date to run 
Example:

In Activity1 there is a datefield if I enter 1/1/2021 I want the activity2 runs in this date(1/1/2021)

forms;process;workflow

5


15 Jul, 2020
confluenceUser
1
confluenceUser

Try using deadlines

Deadlines and Escalations

There's even a demo app in the link given for you to test it out. From your description, you should use the synchronous execution

15 Jul, 2020
confluenceUser
confluenceUser

Thanks Lan 
I need after submitting the activity1 wait the date and then activity 2 will be available, not if the user did not complete the activity one .
It can be done by adding an activity that no one will submit it and route to check if this activity is submited

but I am asking if there is a better way

16 Jul, 2020
confluenceUser
confluenceUser

Yeah, you can use the deadline to trigger on a specific date. Sorry, should've given this link instead.

How to make activity wait/sleep for specific date


21 Jul, 2020
confluenceUser
confluenceUser

This is my question link?

21 Jul, 2020
confluenceUser
confluenceUser

oops sorry...here's the correct link.

Trigger Deadline based on specific Date value